click image to enlarge |
In this photo, a plumber cut the top flange on this engineered floor
joist. With the floor joists paced 24 inches on center, and with
the concentrated load of a toilet above. This was an accident waiting
to happen. In order to solve this problem, an engineer from the floor
joist manufacturer was contacted to design a fix. |
click image to enlarge |
This is an example of a contractor countersinking the foundation
anchor bolts in to the mudsill. The mudsill is the point of attachment
for the exterior wall framing, and with better then half of the wood
missing. This weakens the hold down of the foundation anchor bolt. |
click image to enlarge |
The flange on this engineered floor joist was cut and weakened the
joist. |
click image to enlarge |
Another example of the flange on an engineered floor joist product
being cut. |